TURNER RAMP

Significant concrete repair and supplemental post-tension structural support work has been completed over the 2017 construction season. A new traffic wearing surface has been applied to approximately one half of the roof, after a great deal of old asphalt material was removed from the roof. A new traffic surface was installed on portions of the roof as weather permitted. Most parking spaces removed from service during construction will be returned to service by December 4, 2017. Additional drain repair work and connections will be completed over the next few weeks, concluding work for this construction season. Work on this $2.16M project will continue in the 2018 construction season.